Pennsylvania Code (Last Updated: April 5, 2016) |
Title 25. ENVIRONMENTAL PROTECTION |
PART I. Department of Environmental Protection |
Subpart C. Protection of Natural Resources |
Article II. Water Resources |
Chapter 105. Dam Safety and Waterway Management |
SubChapter B. DAMS AND RESERVOIRS |
Section 105.108. Completion, certification and project costs
-
Within 30 days after the final inspection or within 30 days of completion of the work if the final inspection is waived by the Department, the permittee or owner shall file with the Department a completion certification provided by the Department stating that work has been performed in accordance with the terms and conditions of the permit or other Department authorization; the approved maps, plans, profiles and specifications; and applicable laws and the provisions of this title. The completion certification must contain the following:
(1) Original signature of the permittee or owner.
(2) Seal and original signature of the supervising engineer.
(3) Design cost.
(4) Construction cost.
(5) Construction inspection cost.
(6) Estimated percentage of the total cost for each major feature of the project.
The provisions of this § 105.108 adopted January 7, 2011, effective January 8, 2011, 41 Pa.B. 219.
Notation
The provisions of this § 105.108 issued under section 5 of the Dam Safety and Encroachments Act (32 P. S. § 693.5).
This section cited in 25 Pa. Code § 105.13 (relating to regulated activitiesinformation and fees); 25 Pa. Code § 105.88 (relating to dam permit issuance); and 25 Pa. Code § 105.111 (relating to commencement of storage of water, fluid or semifluid).