Section 87.157. Cessation of operations: temporary
-
(a) As soon as it is known that the operation will temporarily cease for more than 30 days, the operator shall submit a notice of intention in writing to temporarily cease the operation. The notice shall include a statement of the exact number of acres that will have been affected in the permit area, the extent and kind of reclamation of the areas and identification of the backfilling, regrading, vegetation, monitoring and water treatment activities which will continue during the temporary cessation.
(b) Temporary cessation of an operation may not exceed 90 days unless the Department approves a longer period not to exceed 180 days or unless the Department approves a longer period for reasons of seasonal shutdown or labor strike.
(c) Temporary cessation does not relieve the operator of the obligations to comply with the permit.
The provisions of this § 87.157 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective July 31, 1982, 12 Pa.B. 2382; amended June 15, 1990, 20 Pa.B. 3383, effective July 27, 1991, 21 Pa.B. 3316. Immediately preceding text appears at serial pages (148694) to (148695).