(a) General rule. The district engineer shall be authorized to permit temporary use by public agencies and charitable organizations of right-of-way not required for free movement of traffic.
(b) Duration. A permit for temporary use of right-of-way may not exceed 90 days duration.
The provisions of this § 495.7 adopted May 9, 1975, effective May 10, 1975, 5 Pa.B. 1230; readopted August 5, 1988, effective August 6, 1988, 18 Pa.B. 3434. Immediately preceding text appears at serial page (113709).