Section 57.147. Scheduled imports and exports  


Latest version.
  • The Annual Resource Planning Report (ARPR) shall include a forecast of scheduled imports and exports in megawatts for the EDC, the EDC’s control area and appropriate regional reliability council, as defined under § 57.192 (relating to definitions).

    (1) Actual data for the past year and estimated data for the ensuing 5 years shall be provided.

    (2) The data shall be provided for both summer and winter seasons, the latter being the winter following the summer of the past year.

    (3) A breakdown of scheduled imports and exports shall be provided including the name and type of each participating entity.

The provisions of this § 57.147 amended February 25, 2000, effective February 26, 2000, 30 Pa.B. 1129. Immediately preceding text appears at serial pages (205871) to (205872).

Notation

Authority

The provisions of this § 57.147 amended under the Public Utility Code, 66 Pa.C.S. § § 501, 524, 1501, 1504 and 2809.