SubChapter K. UPGRADING OF COAL-FIRED GENERATING UNITS |
Section 57.125. Refunds
Latest version.
-
Under 66 Pa.C.S. § 514 (relating to use of coal), revenue collected under § 57.124(b) (relating to special cost recovery) is subject to refund with interest, as specified under 66 Pa.C.S. § 514(c), if a qualified project is not completed within 2 years from the end of the test period in which the project was initially claimed and qualified.