Appendix A. Money Back Guarantee Permit Review Program


Latest version.



  • Permit Process Steps in Calendar DaysPublic
    PERMIT NAME
    No./yearAdm.1 Tech2 TechDec RevTotalCom-
    RevRevRevTimement*
    Oil & Gas Well Drilling1,35052500300
    Coal Surface Mining135760303012760
    Noncoal Surface Mining39760303012760
    Coal Underground Mining10760303012760
    Radioactive Material License2131000130
    Air Plan Approval-Minor New Source Reviews5501555555518030
    Municipal and Residual Waste Processing and Composting Facilities72060303014060
    Land Application of Municipal or Residual Waste1362060303014060
    Municipal Waste Beneficial Use Approvals192060303014060
    Municipal and Residual Waste Transfer Facilities602060303014060
    Form U for Residual Waste (with approved waste acceptance plan)1,50001500150
    NPDES New2152060309020060
    NPDES Major Renewals802080409023060
    Public Water Supply5502080503018030
    Water Obstructions and Encroachment5002060252513030
    Dam Safety8020100505022030

    *Public comment time is shown for information only and should not be added to total time. Public comment time is already factored into technical and decision review times.

    NOTE: •All authorizations and related processing times are for individual permits only. General permits, when applicable, are processed in less time.•All time is shown in DEP calendar days. The time an applicant may take to prepare or modify an application is not included.