Section 405.3. Permit application  


Latest version.
  • (a) An owner of an elevator or lifting device or an authorized agent shall apply to the Department for a permit before the construction, alteration, replacement or repair of an elevator or lifting device.

    (b) An owner or owner’s agent shall submit four copies of a permit application and supporting documents to the Department for review. The application and supporting construction documents shall be submitted in Department-approved media and clearly detail the location, nature and extent of the proposed construction and its compliance with the Uniform Construction Code.

    (c) The Department may suspend or revoke a permit when the permit was issued erroneously, on inaccurate, incorrect or incomplete information or issued in violation of the Uniform Construction Code. The Department may charge an applicant a new application and inspection fee when a previous permit was suspended or revoked based upon inaccurate, incomplete or incorrect information provided by the permit applicant.

    (d) A permit becomes invalid unless construction work is commenced within 180 days after its issuance or if the work is suspended or abandoned for a period of 180 days after it is commenced. The Department may grant written extensions of time for periods of 180 days each. A permit remains valid for no more than 5 years.

    (e) The Department will grant or deny a permit in whole or in part within 30 business days of the filing date of a complete application. The Department will provide written notification to the applicant for applications denied in whole or in part.

    (f) The Department will place the written or stamped notation ‘‘Reviewed and Approved for Code Compliance’’ on the documents accompanying the permit application. The Department will keep three sets of the construction documents and send one set of construction documents to the permit applicant.

    (g) An owner or owner’s agent may request a variance or appeal the code administrator’s decision to the Industrial Board under § 403.122 (relating to appeals, variances and extensions of time). The appeal shall be based on a claim that the true intent of the act or the Uniform Construction Code were incorrectly interpreted, the act does not fully apply or an equivalent form of construction is to be used.

    (h) A permit is not valid until the Department collects the required fees under § 401.2 (relating to Department fees).