Pennsylvania Code (Last Updated: April 5, 2016) |
Title 25. ENVIRONMENTAL PROTECTION |
PART I. Department of Environmental Protection |
Subpart D. Environmental Health and Safety |
Article VIII. Municipal Waste |
Chapter 283. Resource Recovery and Other Processing Facilities |
SubChapter C. OPERATING REQUIREMENTS |
Section 283.271. Temporary shutdown
Latest version.
-
(a) An alternate permitted solid waste processing or disposal facility shall be available for use if the facility is shut down for a period that extends beyond the permitted storage capacity of the facility. The Department may waive this requirement if the facility has a second processing line that can be used if the first processing line is shut down.
(b) If the incinerators at the facility are out-of-service for a longer period than the storage capacity of the site will allow, solid waste shall be removed from the site.