Pennsylvania Code (Last Updated: April 5, 2016) |
Title 25. ENVIRONMENTAL PROTECTION |
PART I. Department of Environmental Protection |
Subpart D. Environmental Health and Safety |
Article IX. Residual Waste Management |
Chapter 291. Land Application of Residual Waste |
SubChapter C. GENERAL OPERATING REQUIREMENTS FOR THE LAND APPLICATION OF RESIDUAL WASTE |
Section 291.207. Water supply replacement
-
(a) An operator which adversely affects a water supply by degradation, pollution or other means shall restore the affected supply at no additional cost to the owner or replace the affected water supply with an alternate source that is of like quantity and quality to the original supply at no additional cost to the owner.
(b) A temporary water supply shall be provided as soon as practicable but not later than 48 hours after one of the following:
(1) Receipt of information showing that the operator is responsible for adversely affecting the water supply.
(2) Receipt of notice from the Department that the operator is responsible for adversely affecting the water supply.
(c) A permanent water supply shall be provided as soon as practicable but not later than 90 days after one of the following:
(1) Receipt of information showing that the operator is responsible for adversely affecting the water supply.
(2) Receipt of notice from the Department that the operator is responsible for adversely affecting the water supply.
(d) Permanent water supplies include development of a new well with a distribution system, interconnection with a public water supply or extension of a private water supply, but do not include provision of bottled water or a water tank supplied by a bulk water hauling system, which are temporary water supplies.
The provisions of this § 291.207 amended January 12, 2001, effective January 13, 2001, 31 Pa.B. 235. Immediately preceding text appears at serial page (239031).