Section 289.151. Soil erosion and sedimentation control plan  


Latest version.
  • (a) The applicant shall submit a plan to manage surface water and control erosion during all phases of construction and operation at the proposed facility. The plan shall be based on the requirements of Chapter 102 and § § 289.252—289.254 and other applicable State and Federal requirements. Calculations indicating water quantities shall be based on the 24-hour precipitation event by inches to be expected once in 25 years.

    (b) The plan shall include fully dimensioned diversion ditches, indicating length, gradient and cross section for configuration by reach, and capacities for ditch volume by reach. The calculations which are necessary to support design and siting shall be included in the plan.

Notation

Cross References

This section cited in 25 Pa. Code § 289.131 (relating to basic requirements).