Section 105.103. Weather and ground conditions  


Latest version.
  • (a) No earth or other embankment material may be covered, placed, compacted, or graded when in a frozen condition.

    (b) Masonry and concrete may not be placed in freezing weather except under conditions approved by the Department.

The provisions of this § 105.103 adopted September 10, 1971, effective September 11, 1971, 1 Pa.B. 1804; amended August 11, 1978, effective August 28, 1978, 8 Pa.B. 2229; amended September 26, 1980, effective September 27, 1980, 10 Pa.B. 3843; amended January 7, 2011, effective January 8, 2011, 41 Pa.B. 219. Immediately preceding text appears at serial page (207724).

Notation

Authority

The provisions of this § 105.103 amended under section 5 of the Dam Safety and Encroachments Act (32 P. S. § 693.5).