  • (a) Priority points attributable to this factor shall be assigned as follows:

    Project Equivalent PopulationPriority Points
    1—3,500 6
    3,501—5,000 7
    5,001—10,000 8
    10,001—50,000 9
    greater than 50,00010

    (b) Project Equivalent Population shall be the initial population equivalent to be served by the project at the time that the project is rated.

The provisions of this § 103.9 adopted September 2, 1971, effective September 3, 1971, 1 Pa.B. 1804; amended December 28, 1973, effective December 29, 1973, 3 Pa.B. 2957; amended April 29, 1977, effective May 16, 1977, 7 Pa.B. 1171; amended December 21, 1979, effective December 22, 1979, 9 Pa.B. 4158. Immediately preceding text appears at serial page (30948).