Section 90.307. Treatment of discharges
-
(a) Except for preexisting discharges that are not encountered during coal refuse disposal activities or the implementation of the abatement plan, the operator shall comply with § 90.102 (relating to hydrologic balance: water quality standards, effluent limitations and best management practices).281279
(b) The operator shall treat the preexisting discharges that are not encountered during coal refuse disposal activities or implementation of the abatement plan to comply with the effluent limitations established by best professional judgment. The effluent limitations established by best professional judgment may not be less than the baseline pollution load. If the baseline pollution load, when expressed as a concentration for a specific parameter, satisfies the effluent limitation in § 90.102 for that parameter, the operator shall treat the preexisting discharge for that parameter to comply with either effluent limitations established by best professional judgment or the effluent limitations in § 90.102.
(c) For purposes of subsections (a) and (b), the term encountered may not be construed to mean diversions of surface water and shallow groundwater flow from areas undisturbed by the implementation of the abatement plan that would otherwise drain into the affected area, as long as the diversions are designed, operated and maintained under § 90.104 (b)(h) (relating to hydrologic balance: diversions).
(d) An operator required to treat preexisting discharges will be allowed to discontinue treating the discharges under subsection (b) when the operator affirmatively demonstrates the following to the Departments satisfaction:
(1) The preexisting discharges are meeting the effluent limitations established by subsection (b) as shown by groundwater and surface water monitoring conducted by the operator or the Department.
(2) Coal refuse disposal activities under the permit including the pollution abatement areaare being or were conducted under the requirements of the permit and the authorization, and Chapter 86 (relating to surface and underground mining: general) and this chapter except as specifically modified by this subchapter.
(3) The operator has implemented each step of the abatement plan as approved in the authorization.
(4) The operator did not cause or allow additional surface water pollution or groundwater degradation by reaffecting the pollution abatement area.
(e) If after discontinuance of treatment of discharges under subsection (d) the discharges fail to meet the effluent limitations established by subsection (b), the operator shall reinstitute treatment of the discharges under subsection (b). An operator who reinstitutes treatment under this subsection will be allowed to discontinue treatment if the requirements of subsection (d) are met.
(f) Discontinuance of treatment under subsection (d) may not be deemed or construed to be or to authorize a release of bond under § 90.309 (relating to criteria and schedule for release of bonds on pollution abatement areas).
Notation
This section cited in 25 Pa. Code § 90.309 (relating to criteria and schedule for release of bonds on pollution abatement areas).