Section 88.199. Hydrologic balance: permanent postmining renovation of sedimentation ponds, diversions, impoundments and treatment facilities  


Latest version.
  • At the completion of bank removal and reclamation activities, the person who conducts the bank removal and reclamation activities shall renovate all permanent sedimentation ponds, diversions, impoundments and treatment facilities to meet criteria specified in the detailed design plan for the permanent structures and impoundments.

The provisions of this § 88.199 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382.