Section 83.609. Application by project participants  


Latest version.
  • (a) Applications will be on a one-page form approved by the Commission. Applications should be submitted to the local conservation district at the times designated by the local district. Handwritten applications will be acceptable.

    (b) An application shall be specific to one work location or one type of work and shall include the following:

    (1) A short description of the problem being solved.

    (2) The basis of the cost estimate.

    (3) The proposed project work schedule.

    (4) The basis for successful completion.

    (5) The type of pollution to be reduced.

    (6) Other items specified by the Commission.

    (c) The QAB shall expedite the approval process by inserting additional requirements which become binding when accepted by the applicant.