The interconnection procedures apply to customer-generators with small generator facilities that satisfy the following criteria:
(1) The electric nameplate capacity of the small generator facility is equal to or less than 2 MW.
(2) The small generator facility is not subject to the interconnection requirements of an RTO.
(3) The small generator facility is designed to operate in parallel with the electric distribution system.
Notation