Pennsylvania Code (Last Updated: April 5, 2016) |
Title 52. PUBLIC UTILITIES |
PART I. Public Utility Commission |
Subpart C. Fixed Service Utilities |
Chapter 69. General Orders, Policy Statements and Guidelines on Fixed Utilities |
Section 69.2902. Definitions
-
The following words and terms, when used in § § 69.2901, 69.2903 and 69.2904, have the following meanings, unless the context clearly indicates otherwise:
AEPS ActThe Alternative Energy Portfolio Standard Act (73 P. S. § § 1648.11648.8).
EDCElectric distribution companyThe term has the same meaning as defined in 66 Pa.C.S. § 2803 (relating to definitions).
EGSElectric generation supplierThe term has the same meaning as defined in 66 Pa.C.S. § 2803.
Large-scale solar projectAn alternative energy generation system employing solar photovoltaic technology with a nameplate capacity of 200kW or more.
RFPRequest for proposal.
SREC market priceThe weighted average of all accepted winning bids in response to an EDC RFP for large-scale solar project solar alternative energy credits, as those credits are defined in section 2 of the AEPS Act (73 P. S. § 1648.2).
SRECsSolar renewable energy credits.
Small-scale solar projectAn alternative energy generation system employing solar photovoltaic technology with a nameplate capacity of less than 200kW.
Solar aggregatorA person or entity that purchases for resale, or otherwise consolidates for sale, solar alternative energy credits for resale to EDCs and electric generation suppliers.
Stakeholder working groupA group composed of EDCs, EGSs, Commission staff, public advocates, solar aggregators and other interested parties that meets at least semiannually and proposes to the Commission updates to standardized solar alternative energy credit RFPs and related contracts that are posted on the Commissions web site.
The provisions of this § 69.2902 adopted October 22, 2010, effective October 23, 2010, 40 Pa.B. 6157.
Notation
This section cited in 52 Pa. Code § 69.2901 (relating to purpose).