Section 66.6. Specific requirements for public works subcontractors  


Latest version.
  • (a) Prior to beginning either onsite or offsite work on a public works project when the public works contractor’s contract was executed after January 1, 2013, every subcontractor shall submit a completed Form to the contracting public body. During a public works contract, a new employee hired by a public works subcontractor, regardless of whether he will be working onsite or offsite of a public work or otherwise, shall be verified within 5 business days of his start date.

    (b) Subcontracts between a subcontractor and its subcontractors are required to contain notification of the applicability of the act, information regarding the use of EVP and reference to the Department’s web site at www.dgs.state.pa.us to obtain a copy of the Form.

    (c) A subcontractor shall cooperate with the Department during an investigation or audit arising under the act.