Section 88.332. Cessation of operations: temporary  


Latest version.
  • (a) As soon as it is known that the operation will temporarily cease for more than 30 days, the operator shall submit a notice of intention, in writing, to temporarily cease the operation. The notice shall include a statement of the exact number of acres which will have been affected in the permit area, the extent and kind of reclamation of those areas, and identification of the backfilling, regrading, revegetation, monitoring and water treatment activities that will continue during the temporary cessation. The system for preventing precipitation from contacting the coal refuse shall be installed when the temporary cessation exceeds 90 days. The Department may approve a longer period, not to exceed 1 year, under subsection (b).

    (b) Temporary cessation of an operation may not exceed 90 days unless the Department approves a longer period for reasons of seasonal shutdown or labor strike.

    (c) Temporary cessation does not relieve the operator of the obligation to comply with any provisions of the permit.

The provisions of this § 88.332 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended March 30, 1984, 14 Pa.B. 1143, effective August 10, 1985, 15 Pa.B. 2872; amended July 13, 2001, effective July 14, 2001, 31 Pa.B. 3735. Immediately preceding text appears at serial page (244227).