Section 127.215. Reactivation  


Latest version.
  • (a) A facility which has been out of operation or production for 1 year or more during the term of its operating permit may be reactivated within the term of its operating permit and will not be considered a new facility subject to this subchapter if the following conditions are satisfied:

    (1) The permittee shall within 1 year of the deactivation submit in writing to the Department and implement a maintenance plan which includes the measures to be taken, including maintenance, upkeep, repair or rehabilitation procedures, which will enable the facility to be reactivated in accordance with the terms of the permit.

    (2) The permittee shall submit a reactivation plan at least 30 days prior to the proposed date of reactivation. The reactivation plan shall include sufficient measures to ensure that the facility will be reactivated in compliance with the permit requirements. The permittee may submit a reactivation plan to the Department at any time during the term of its operating permit. The reactivation plan may also be submitted to and approved in writing by the Department as part of the plan approval or permit application process.

    (3) The permittee shall notify the Department in writing within 1 year of deactivation requesting preservation of the emissions in the inventory and indicating the intent to reactivate the facility.

    (4) The permittee shall comply with the terms and conditions of the following:

    (i) Maintenance plan while the facility is deactivated.

    (ii) Reactivation plan and the operating permit upon reactivation.

    (5) The permittee with an approved reactivation plan shall notify the Department in writing at least 30 days prior to reactivation of the facility.

    (b) The Department will approve or disapprove in writing the complete reactivation plan within 30 days of plan submission, unless additional time is required based on the size or complexity of the facility.

    (c) For a facility which is deactivated in accordance with subsection (a), ERCs may be created only if an ERC registry application is filed within 2 years of deactivation.

The provisions of this § 127.215 amended May 18, 2007, effective May 19, 2007, 37 Pa.B. 2365. Immediately preceding text appears at serial pages (221989) to (221990).

Notation

Cross References

This section cited in 25 Pa. Code § 127.11 (relating to plan approval requirements); 25 Pa. Code § 127.11a (relating to reactivation of sources); 25 Pa. Code § 127.13 (relating to extensions); 25 Pa. Code § 127.203 (relating to facilities subject to special permit requirements); 25 Pa. Code § 127.207 (relating to creditable emissions decrease or ERC generation and creation); and 25 Pa. Code § 127.211 (relating to applicability determination).