TURNPIKE COMMISSION Retention of an Engineering Firm [33 Pa.B. 2571] Evaluation and Design of the Ceiling System in the Eastbound Tube of the Tuscarora Tunnel, Milepost 186.20, Huntingdon County Reference No. 2-064 The Turnpike Commission (Commission) will retain an engineering firm to perform the evaluation and design of the ceiling system in the eastbound tube of the Tuscarora Tunnel, located at Milepost 186.20 in Huntingdon County. Study and design services for this contract will include, but not be limited to, cursory inspection of the existing ceiling slabs, evaluation of various ceiling slab replacements or elimination options, submission of a recommendations report and preparation of preliminary and final construction plans and specifications for the Commission to let one construction contract.
The following factors will be considered by the Commission during the evaluation of the firms submitting Letters of Interest for this project:
a. Specialized experience and technical competence of prime consultant and subconsultants. The team must clearly demonstrate an ability to analyze available data to make decisions and develop plans to complete the project in a timely and cost effective manner.
b. Past record of performance with respect to cost control, work quality, ability to meet schedules and previous experience on similar projects. The consultant should identify similar projects that have been completed by that firm as the prime, the magnitude of the project and the client.
c. The specific experience and number of individuals who constitute the firm. Firms should have sufficient qualified permanent full-time personnel to complete mapping work assignments with short delivery schedules utilizing current state-of-the-art photogrammetric instruments, equipment and software.
d. Workload of the prime consultant and subconsultants for all Department of Transportation (Department) and Commission projects.
e. Other factors, if any, specific to the project.
Address these items and any necessary further details in a brief yet comprehensive manner in the Letter of Interest.
Questions and inquiries concerning this solicitation should be directed to James L. Stump, P. E., (717) 939-9551, Ext. 5540, jstump@paturnpike.com. Contractual questions should be directed to George M. Hatalowich, (717) 986-8737, ghatalow@paturnpike.com.
General Requirements and Information Firms interested in providing the previously described work and services are invited to submit a statement of interest with the required information. The statements of interest must include the following:
1. A one-page transmittal letter clearly identifying the project reference number, brief description of the project from the advertisement, the firm's Federal identification number, the firm's legal name, contact person or project manager, address of corporate office and project office. (If the firm has multiple offices, the location of the office performing the work must be identified.)
2. A three-page expression of interest on the advertised project. Each firm should demonstrate its ability to perform the specific requirements indicated for each project and provide explanation of the technical approach.
3. An organization chart for the project, identifying key personnel and any subconsultants and their roles. Any deviation from the subconsultants listed in the Statement of Interest will require written approval from the Commission.
4. Tabulation or listing of workload for the prime consultant and all subconsultants for all Department and Commission projects. Do not graphically represent the firm's workload.
5. A Consultant Qualification Package similar to the one submitted to the Department for the current year or one that is best suited for this project. A copy of the Consultant Qualification Package printed directly from the Department's ECMS website is acceptable.
The Consultant Qualification Package should contain, at a minimum, the following information for the prime consultant and all subconsultants and attached to the back of the statement of interest (subs to follow primes):
* ECMS General Information and Project Experience Forms or Standard Form (SF) 254--Architect-Engineer and Related Services Questionnaire in its entirety, either not more than 1 year old as of the date of the advertisement.
* Resumes of key personnel expected to be involved in the project (limit to two 8 1/2" x 11" pages per person). Only resumes of key personnel should be included.
* Copy of the firm's registration to do business in this Commonwealth as provided by the Department of State for firms with out-of-State headquarters or corporations not incorporated in this Commonwealth.
* A copy of the Department's DBE/WBE certification, if applicable.
Small firms, DBE firms, and other firms who have not previously performed work for the Commission are encouraged to submit a statement of interest.
Firms interested in performing the previously described services are invited to submit a statement of interest and required information to George M. Hatalowich, Engineering Contract Manager, Turnpike Commission Administration Building, 700 South Eisenhower Boulevard, Middletown, PA 17057 (street address). The Commission mailing address is P. O. Box 67676, Harrisburg, PA 17106-7676.
The Statement of Interest and required information must be received by 12 p.m., Thursday, June 12, 2003. Statements of interest received after this date and time will be time-stamped and returned.
Based on an evaluation of acceptable Statements of Interest received in response to this solicitation, one firm will be selected for each contract. The order of preference will be established for the purpose of negotiating an agreement with the highest ranked firm established by the Technical Review Committee and approved by the Commission. Technical Proposals will not be requested prior to the establishment of the final ranking.
The Commission reserves the right to reject all Statements of Interest, to cancel solicitation requested under this notice and/or to readvertise solicitation for the work and services.
MITCHELL RUBIN,
Chairperson[Pa.B. Doc. No. 03-1022. Filed for public inspection May 23, 2003, 9:00 a.m.]